BUILDING SCHEDULE - For Subcontractors, Suppliers, Craftsmen
|
SCHEDULE - Final Week to C.O.
|
Certificate of Occupancy Issued December 18th at 5pm, 2008. WOW!
THANK YOU everyone who has had a hand in the construction of this wonderful home!
|
 |
| Mountain Glassworks Fits Countertops |
|
|
NOTES: Final Inspections scheduled for Thursday a.m. December 18th.
|
ONE DAY to FINAL
Still to Complete:
Hot Water; dishwasher
Radiant Heat: Zone thermostats and ready for inspections
HVAC: Finish installing vent grills
Electrical: Finish electrical to gate; hook up generator; walkway electrical; floor outlets.
Low Voltage and Lighting: finish security system, test fire and safety alarms; fire alarm certificate
|
Final 30 Days
December 1 - Electrical Final Re-inspection by Building Department COMPLETE December 1-3 - Elevator Completion by Blue Moose Elevators COMPLETE minus 1 switch ordered Floor 2 December 2 - Drywall Completion and Touch-ups by G&H Drywall - COMPLETE December 3 - Countertops, MB and Kitchen by Mountain Glass and Granite - COMPLETE December 3 - First Full Clean by Richard MacCrea - COMPLETE December 8 - Lightning Protection System Finish by Wolf Corp. COMPLETE December 9 - Waterfall Kit Delivery by Urdles of Delray Beach, Florida (keep parking lot clear) COMPLETE December 4 -8 - Final Stain, Varnish, Paint and Paint Touch-Up by George (house needs to be clear of other work teams except boiler installers, HVAC, electric, or plumbers)COMPLETE December 8 - Electric Co. Set Meter COMPLETE December 8 - Kitchen Vent hood goes in ahead of flooring COMPLETE December 8 & 9 - Set Generator COMPLETE December 10 - Finish Gate install by M&M Fencing (Danny)COMPLETE awaiting final electrical December 5 - 10 - Boiler installation and Radiant Hookups by Christian Plumbing December 10th - Plumbing Trim Outs December 10 - Propane Hookups (boiler, furnace) by Suburban Propane COMPLETE December 9 - 12 - HVAC Complete and tested by CSM Heating and Cooling December 10 - DIRECTV satellite dish install and test by DIRECTV COMPLETE December 10 - Phone - COMPLETE December 12 - Wood Floors by Mountain Interiors (all other work teams restricted to Basement Floor) COMPLETE December 16 - Floors - carpet by Mountain Interiors (other work teams restricted to top floor) December 12 - Final Propane hookups - appliances - Suburban Propane COMPLETE December 15 - Finals on trim and cabinetry December 16 - Finish Electrical by BCH December 17 - Final Testing, HVAC grills and ducts complete, low voltage systems testing - CSM, BCH, Cardinal Group
December 18th - FINAL INSPECTIONS PASSED!
December 17, 18 - Closet Cabinets by Closet Clinic December 18 - Shower Doors and mirrors by Mountain Glass and Granite December 19 - Second and Final Full Clean by Richard MacCrea December 20 - 23 - Electronics hookups, system test, trims complete December 22 - Landscape Plants by Smoky Mountain Landscapes
|
 |
| Freddy and Helper of Blue Moose Elevators perform initial installation of cab |
|
|
Final Electrical Re-inspection PASSED Monday, December 1st. Meter to be set December 8th. COMPLETE
|
 |
| George's Team of painters! |
|
|
 |
| Walt Sofield Installs backsplash in kitchen |
|
|
|
|
 |
| Ricky of Christian Plumbing starts plumbing final in master bath |
|
|
 |
| Joe installs railing wires |
|
|
 |
| Countertops by Mountain Glassworks |
|
|
Framing and Roughs PASSED inspection September 18th INSULATION and Piping PASSED October 3rd
|
Interested in supplying a service or product? Call Lisa Turner: 561-866-0011 Note: You must be licensed and insured to work on CliffHangar. A Certificate of Insurance must be provided prior to commencement of work.
|
NOTE: Framing and Rough Inspections were conducted by Sam Beck on Thursday, Sptember 11th. Most of the corrections involve framing and the stairway, the other items are minor and being corrected now. We expect another inspection to be called in for Thursday, September 18th. Insulation is scheduled for Monday, September 22nd. -Lisa
BUILDING DEPARTMENT CORRECTIONS LIST - BLUE means COMPLETE
PLUMBING:
Vent Pipe for Water Heater
HVAC:
Two methods of overflow control for condensate lines (need sensor in pan) Caulk Air Return, Study Water in ducting
GAS Drip T in Manifold 2
ELECTRONIC/LOW VOLTAGE Need outside rated wiring on bridge/walkway
ELECTRICAL No issues
GENERAL Tempered window needed in stairway
FRAMING Joist Hangars above elevator shaft Squash blocking for i Levels/Joists Solid blocking - Draft Stop at ceiling height all dropped ceilings Solid blocking at top of stair treads @ i-level Need 6'8" clearance on staris Bolt deck board to floor board
|
May 9th, 2008 - First Foundation Pour (Footers) by Taylor Concrete May 11th - Walls by Taylor Concrete May 9th - May 27th - Termite Treatments by Critter Cops May 29th - Waterline run by Christian Plumbing May 27th - Garage Slab Pour by Michael's Concrete June 2nd - Framing Begins by Tomas Gebel and craftsmen June 19th - Waterproofing and FoamBoard by Ricky McConnell, Superior Waterproofing June 19th - Windows and Doors delivered by Pella, Jeff Penland July 3rd - West Side Windows In July 8th - Fireplace Rock delivered by DECKERS July 9th - Holly Trees planted by Tim McOwen July 16th - Plumbing Rough by Christian Plumbing July 16th - Fireplace delivered by The Fireplace store - Rick Conner July 21st - Painting - Exterior - begins by Tomas Gebel - West side July 21st - Stucco begins by Tomas Gebel July 28th - Finish interior framing; house dried in July 26th - Gutters install by Hohmann Brothers July 24th - Landscaping Fill and Road Rough by Lisa Turner July 28th - HVAC Rough by CSM Heating and Cooling July 30th - East side grading and backfill begins by Alvin Ray Ledford July 30th - Siding by Tomas Gebel Aug 2nd - Bridge and Walkway design complete - David Hourdequin, Engineer August 2nd - Fireplace Drywall and insulation installed, 2 hour fire rating - G&H Drywall, Inc. - German and Al Heredia August 7th - Fireplace installation by The Fireplace, Rick Conner August 5-11 - Backfill, East side, Retaining Wall, Ledford Grading/Max Taylor August 11th - August 25th- Electrical Roughs by BCH Electric August 11th - Security and Electronics Rough by Cardinal Group, Inc. August 8th - Lightning Rods installed - Christian Wolf, Wolf Corp. August 19th - Retaining Wall, Driveway, Pour - Max Taylor Concrete Foundations August 19th - Walkway and Bridge Pier - First 8 - Michael's Concrete August 21st - Roof by Matt Jones, Advanced Systems Roofing August 27th - Finish outside paint and Rock by Tomas September 2nd- Radiant Heat by Christian Plumbing September 10th - INSPECTIONS - mechanicals rough and framing - FAIL September 11th - Backfill driveway wall by Alvin Ledford September 18th - Re-inspections, framing and roughs September 22nd - Driveway grade by Alvin Ray September 25nd - Insulation by BKP - Tim Whitney September 27th - Driveway Pour by Michael's Concrete October 1 - Inspection October 6th - Drywall start by G&H Drywall October 22nd - Drywall complete October 23th - Paint by George October 29th - Complete decks, platform, sub-basement by Tomas Gebel October 29th - Stain doors, ceiling cedar and beam by George November 5th - Floors Begin, By Mountain Interiors, Inc. November 6th - Trim and Doors by Tomas Gebel November 10th - Beams and Trim, entry deck by Tomas Gebel November 12th - HVAC units set and plumbed November 13th - Generator set and hooked up November 17th - Electrical Trim Out by BCH November 17th - HVAC Finals by CSM November 17th - Smart Home and Low Voltage Trim outs by Cardinal November 17th - Plumbing Trim outs and boiler installation by Christian Plumbing November 19th - Cabinets installation by Mountain Millworks November 20th - MB shower tile complete and shower doors by Mountain Glassworks November 20th - Countertops Template by Mountain Glassworks November 20th - Breakfast Booth and Bookcases by Tomas November 25th - Radiant Heat Trim Outs by Christian Plumbing November 25th - Plumbing Trim outs Start November 28th - Electrical Inspection November 28th - Boiler Installation November 28th - Kitchen Appliances December 1st - Elevator Trim Out December 1st and 2nd - Drywall Complete and Touchup; Elevator Shaft December 8th - Landscaping by Smoky Mountain Landscapes December 8th - Final trim, testing, paint touch ups December 8th - Flooring by Mountain Interiors December 15th - Final Clean by Richard MacCrea December 16th - Final Test, trims, HVAC, all systems December 18th - Final Inspections and CO
SEE "LAST 30 DAYS" above for DECEMBER 2008 SCHEDULE
ON SCHEDULE
|
 |
| Jessie - G&H Drywall |
|
| |
 |
| The Hohmann Brothers! The Gutter Guys Take on a Monumental Task. |
|
|
 |
| The Corner Tub Survives in spite of being on its end! |
|
|
 |
| Sean and Eric Bring in the Shower! |
|
|
|
|
 |
| Lisa Goes Floor Shopping |
|
|
|